Moorebank
industrial
2019
8 weeks
1300
This industrial roofing project in Moorebank involved the removal of an ageing roof system and its replacement with a new corrugated profile designed for durability, weather protection, and improved internal conditions. The scope included the installation of whirly birds and skylight sheeting to enhance ventilation and natural light throughout the facility.
Replacing a large-scale industrial roof over an operational site required careful planning to manage safety, sequencing, and weather exposure. Coordinating roof removal while integrating new ventilation and skylight elements added complexity, particularly across a 1,300 m² footprint.
Ensuring consistent quality and watertight performance across the entire roof area was critical to the success of the project.
Austek delivered the project through a staged roof replacement approach, allowing the existing roofing to be safely removed and replaced with new corrugated sheeting over the eight-week program. Whirly birds were strategically installed to promote passive ventilation, while skylight sheeting was incorporated to increase daylight penetration and reduce reliance on artificial lighting.
The finished roof provides a durable, low-maintenance solution tailored to industrial use, delivering improved performance and longevity.
The integration of passive ventilation and natural daylight significantly improved the internal environment of the facility. Whirly birds assist in reducing heat build-up, while skylight sheeting introduces consistent natural light—creating a more comfortable and functional workspace.
Combined with the strength and reliability of the new corrugated roof system, the upgraded structure supports better airflow, reduced internal heat load, and long-term operational efficiency—ensuring the building performs reliably well into the future.
From large-scale commercial developments to residential homes, Austek delivers quality roofing solutions across Sydney.
Residential Roofing Location Bossley park Sector Government Completion 2022 Duration 6 weeks Project Size 3000 roof 1200 walls The Project This government-sector project in Bossley
Residential Roofing Location Clovelly Sector Government Completion 2020 Duration 12 weeks Project Size 3000 The Project This government-sector project at Clovelly Public School involved the