Austek replaces, re-sheets and repairs roofs on factories, warehouses, logistics sites and processing facilities across Sydney and NSW. Most of that work happens over a building that has to keep running while the roof above it comes off, and the way a job is staged matters as much as the sheet that goes back on.
We have been doing this since 2010. Below are three real industrial roofs we have replaced, what each one involved, and how long it took.
| Site | Year | Roof area | Programme | Scope | The constraint |
|---|---|---|---|---|---|
| Rydalmere roof replacement | 2017 | 650 m² | 2 weeks | Full roof removal and replacement, all existing services reinstated, new guttering | Tight two-week window, building kept watertight throughout |
| Moorebank industrial re-roof | 2019 | 1,300 m² | 8 weeks | Ageing roof replaced with corrugated, whirlybirds, skylight sheeting | Operational site, delivered as a staged replacement |
| Silverwater roof replacement with safety rails and walkways | 2018 | 400 m² | 4 weeks | Full replacement to Speed Deck, safety rails and walkways integrated | Live industrial environment, safe access maintained at height |



Read the table by programme rather than by area. The smallest roof of the three, Silverwater, ran twice as long as Rydalmere. Its scope also included safety rails and walkways, in a live industrial environment. Moorebank was twice the area of Rydalmere and ran four times as long. It was a staged replacement over an operating site, and it added whirlybirds and skylight sheeting.
That is the honest answer to “how long will our re-roof take”: area sets the materials, scope and site conditions set the programme. A quote that gives you a duration without asking about your operating hours has not planned the job.
1. Inspection. Someone gets on the roof and underneath it. Sheeting, fixings, flashings, gutters, penetrations, safety systems and the structure visible from inside. This is what a commercial roof inspection covers, and on an industrial building it is the step that decides between repair and replacement.
2. Scope and staging plan. Which bays come off first, what has to stay dry underneath, which services need isolating, and where deliveries and cranes go so they do not block your loading docks.
3. Pre-start documentation. Safe work method statements, access and exclusion zones, and the plan for any fragile surfaces such as old skylights.
4. Staged replacement. On an operating site the roof is opened only as far as can be closed again before weather or end of shift. Moorebank was delivered this way over eight weeks.
5. Services, drainage and handover. Plant and penetrations reinstated and flashed, gutters connected, and the roof left with safe access for whoever maintains it next.
You will get a faster and more accurate price if you can tell us:
We work with materials from Australian manufacturers including Colorbond steel by BlueScope, Lysaght and ARCPANEL. Profile, substrate and coating are specified to the building: span between purlins, roof pitch, what the building is used for, and how corrosive its location is. For the detail on material choices, compliance and maintenance planning, read our complete guide to industrial roofing in Australia.
Yes. We provide free, no-obligation quotes for industrial roofing and cladding work. On larger roofs the quote follows a site inspection.
Warehouses, factories, logistics centres, processing facilities and large commercial and industrial buildings across Sydney and NSW.
Yes. Works are staged and sequenced with your site manager so the building stays operational. Moorebank and Silverwater were both replaced over working sites.
Yes, for leaks, storm damage and urgent roofing hazards. Our maintenance and repairs team is available 24/7 for emergency call-outs across Sydney. Ongoing work is covered under industrial roof repairs and maintenance.
Asbestos roofing removal is separate regulated work under SafeWork NSW requirements, carried out by a licensed asbestos removalist and planned before any sheet is lifted. Tell us at the quote stage if your register lists it.
A safe work method statement for the task, a current certificate of currency for public liability and workers compensation, and a written programme. Ask before anyone attends site.
The cheapest point to fix an industrial roof is before water reaches stock, production or electrical plant. Send us the site address and roof area and we will arrange an inspection and a staged scope.
For offices, retail, developments and public buildings, see commercial roofing.

Heavy-duty roofing systems for factories & facilities.

Large-scale roofing for offices, warehouses & developments.

New builds, re-roofs & maintenance for homes.

Installation & certification of safety access solutions.

Integrated solar panel and roofing solutions.

Fast, reliable roof leak & storm damage repairs.

Heavy-duty roofing systems for factories & facilities.

Large-scale roofing for offices, warehouses & developments.

New builds, re-roofs & maintenance for homes.

Installation & certification of safety access solutions.

Integrated solar panel and roofing solutions.

Fast, reliable roof leak & storm damage repairs.